A project manager observes that team velocity has dropped significantly over the past three sprints despite no change in team composition. What should the project manager investigate FIRST?
-
A
Whether team members are working enough overtime hours
-
B
Potential impediments, team morale, or process bottlenecks affecting productivity
-
C
Whether the estimation process was flawed from the beginning
-
D
If the product owner is adding too many features to the backlog