A project manager notices that two senior developers frequently clash during sprint reviews, causing tension for the entire team. According to PMBOK, what is the BEST first step?
-
A
Escalate the conflict to the project sponsor immediately
-
B
Address the conflict privately with each developer to understand their perspectives
-
C
Reassign one developer to a different project to eliminate friction
-
D
Allow the conflict to resolve itself through natural team dynamics