A project manager is working on a large infrastructure project with hundreds of stakeholders. Which approach is MOST effective for managing this complexity?
-
A
Communicate identically with all stakeholders to ensure consistency
-
B
Segment stakeholders into groups and tailor engagement strategies per group
-
C
Focus only on stakeholders with the highest authority
-
D
Delegate all stakeholder communication to team leads