A project manager notices that a key stakeholder has high interest but low power. What is the recommended engagement strategy?
-
A
Manage closely with frequent updates
-
B
Keep informed with regular communication
-
C
Monitor with minimal effort
-
D
Keep satisfied with one-on-one meetings