A project has EAC of $620,000 and BAC of $580,000. What does this indicate?
-
A
The project is expected to finish $40,000 over budget
-
B
The project is expected to finish $40,000 under budget
-
C
The project is ahead of schedule
-
D
The project's CPI is greater than 1.0