A hybrid project manager is deciding which elements to manage using predictive vs. agile approaches. Which factor MOST strongly favors using a predictive approach for a component?
-
A
The team is co-located and highly collaborative
-
B
Requirements are well-defined, stable, and unlikely to change
-
C
Stakeholders want frequent delivery of working features
-
D
The technology stack is new and not well understood