In the context of hybrid project management, what is a 'rolling wave' planning approach?
-
A
Planning all project phases in detail at the start
-
B
Planning near-term work in detail while leaving future phases at a higher level
-
C
Continuously rolling back to a previous plan when risks emerge
-
D
Alternating between agile and waterfall phases on a fixed schedule