A project team using a hybrid approach has fixed regulatory deliverables but uncertain technical requirements. How should the project manager structure the work?
-
A
Use waterfall for the entire project to maintain control
-
B
Apply waterfall planning to regulatory milestones and agile iterations for technical development
-
C
Use agile for everything and adjust regulatory deliverables as needed
-
D
Outsource regulatory work to avoid conflicts with the agile team