When using a power/interest grid, how should a project manager manage stakeholders classified as high power and low interest?
-
A
Manage closely with frequent detailed updates
-
B
Keep satisfied with periodic updates without overwhelming them
-
C
Monitor with minimal effort
-
D
Keep informed through regular communications