PMBOK - Project Management Body of Knowledge Practice Test

PMBOK PMBOK Earned Value Management (EVM) Questions and Answers 3

Free · Instant Results

A project has EV = $200,000, PV = $250,000, and AC = $220,000. What is the Schedule Variance (SV)?
▶ Start Practice Test