A stakeholder with high power but low interest has suddenly started attending project meetings and questioning decisions. What is the best course of action?
-
A
Ignore the change since they previously showed low interest
-
B
Reassess their position on the power/interest grid and update the engagement strategy
-
C
Limit the information shared with them to prevent interference
-
D
Ask the project sponsor to restrict their involvement