An organization is adopting Scrum and suggests forming separate 'front-end' and 'back-end' teams that must coordinate to deliver a single Increment. Why does this organizational structure conflict with the Scrum framework's definition of a Scrum Team?
-
A
It introduces dependencies between teams, which can impede the creation of a 'Done' Increment within a single Sprint.
-
B
It violates the Scrum Guide's rule that a Scrum Team must be 10 or fewer people.
-
C
It makes it impossible for the Product Owner to manage a single Product Backlog.
-
D
It requires more than one Scrum Master to facilitate communication between the teams.