A client has requested a significant change to the HVAC system in a commercial building project that is already 50% complete. This change will affect the project's cost and schedule. What is the FIRST document the general contractor should prepare to address this request?
-
A
A Request for Information (RFI)
-
B
A Change Order
-
C
A Subcontractor Agreement Amendment
-
D
A Project Schedule Update