During a project, a subcontractor discovers a discrepancy between the architectural drawings and the structural plans, making it impossible to install a specified beam. What is the first formal step the general contractor should take to resolve this ambiguity?
-
A
Issue a Change Order to the subcontractor with a proposed solution.
-
B
Submit a Request for Information (RFI) to the architect or engineer.
-
C
Proceed with the installation based on their best judgment to avoid delays.
-
D
Document the issue in the daily log and wait for the next project meeting.