A contractor is in the very early stages of planning a project, before detailed architectural drawings are available. The client needs a rough cost projection to determine if the project is financially viable. Which type of estimate is most appropriate at this stage?
-
A
A detailed estimate
-
B
A bid estimate
-
C
A conceptual estimate
-
D
A quantity takeoff estimate