A hospital is planning a major renovation of its surgical suites, which are located adjacent to the neonatal intensive care unit (NICU). Which of the following is the MOST critical first step in the project planning process to mitigate risks to vulnerable patients?
-
A
Finalize the construction budget and schedule.
-
B
Select the architectural firm and general contractor.
-
C
Conduct a multi-disciplinary Infection Control Risk Assessment (ICRA).
-
D
Notify the local fire marshal of the planned construction.