A Six Sigma Black Belt notices that two team members consistently disagree during tollgate reviews, causing project delays. Which conflict resolution approach is most appropriate?
-
A
Forcing a decision by siding with the senior team member
-
B
Facilitating a structured discussion to identify the root cause of disagreement
-
C
Removing both members from the project team
-
D
Ignoring the conflict and proceeding with the majority opinion