Pre-Lift Planning & Load Chart Interpretation Flashcards
6 cards from real OSHA practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 Pre-Lift Planning & Load Chart Interpretation flashcards as text
Which document defines the crane's maximum allowable wind speed for safe operation?
Answer: The crane manufacturer's load chart and operator's manual
The manufacturer's load chart and operator manual specify wind speed limitations that must not be exceeded during operation.
When using a mobile crane on a slope, what is the general OSHA-aligned rule regarding level setup?
Answer: The crane must be set up level per the manufacturer's specifications, typically within 1% grade
Manufacturers typically require cranes to be set up level within 1% (about 0.6°) to maintain rated capacity and stability.
What information must be confirmed about the load before referencing the load chart?
Answer: Load weight, center of gravity, and attachment points
Knowing the load's weight, center of gravity, and attachment points is essential to select proper rigging and correctly apply the load chart.
A lift plan requires a crane to work near overhead power lines. What is the minimum clearance required under OSHA 1926.1408 for lines up to 50 kV?
Answer: 10 feet
OSHA 1926.1408 requires a minimum 10-foot clearance from power lines up to 50 kV unless the utility has de-energized and visibly grounded the line.
During pre-lift planning for a tandem (two-crane) lift, what must be calculated for each crane?
Answer: Each crane's share of the load, its percent of rated capacity, and its individual lift plan
Each crane in a tandem lift must have its individual load share calculated, verified against its rated capacity, and documented in the plan.
What is the role of a lift director on a critical or multi-crane lift under OSHA 1926.1431?
Answer: To direct the operations, ensuring the lift plan is followed and all personnel are briefed
OSHA 1926.1431 requires a qualified lift director to oversee critical and multi-crane lifts, coordinate personnel, and ensure the written plan is executed correctly.