When performing a critical lift (load exceeding 75% of the crane's rated capacity), what is required before the lift begins?
-
A
A written critical lift plan approved by a qualified person
-
B
Verbal approval from the site supervisor only
-
C
A standard lift plan with no additional requirements
-
D
Notification to OSHA before proceeding