According to ASME B30.5, what must occur if the crane's counterweight configuration is changed between lifts on the same job site?
-
A
The operator may proceed if the change is within 10% of original weight
-
B
A new load chart review must be conducted and the lift plan updated to reflect the new configuration
-
C
Only the site safety officer needs to be notified
-
D
The change is acceptable if the boom length stays the same