A project manager notices that the cost performance index (CPI) is 0.85. What does this indicate?
-
A
The project is under budget
-
B
The project is getting $0.85 of value for every $1 spent
-
C
The project will finish 15% ahead of schedule
-
D
The project has 85% stakeholder approval