The modified benefit-cost ratio (BCR) differs from the conventional BCR in that it:
-
A
Uses the IRR instead of the MARR as the discount rate
-
B
Subtracts disbenefits from the numerator rather than adding them to the denominator
-
C
Excludes initial capital costs from the analysis
-
D
Applies only to government projects costing over $1 million