A contractor receives a change order that increases the project scope. The contractor should:
-
A
Proceed with the work and bill extra at project completion
-
B
Refuse all change orders not in the original contract
-
C
Execute a written change order signed by both parties before starting the additional work
-
D
Notify OSHA before proceeding with any scope change