A project champion asks why the SIPOC diagram is created during the Define phase rather than later. What is the best answer?
-
A
It provides high-level process scope before detailed mapping begins
-
B
It replaces the need for a detailed process map
-
C
It is required by the project charter template
-
D
It identifies root causes of the problem