A Black Belt notices that two team members consistently disagree during meetings, slowing progress. Which conflict resolution approach is MOST appropriate for a Black Belt to use first?
-
A
Escalate to the project sponsor immediately
-
B
Facilitate a structured dialogue to surface underlying interests
-
C
Remove one team member from the project
-
D
Ignore the conflict and let it resolve naturally