According to ISTQB, which of the following is an example of a 'project risk' (as opposed to a product risk)?
-
A
A critical module may contain undetected security vulnerabilities
-
B
Key test personnel may leave the project mid-cycle
-
C
The payment processing feature may calculate totals incorrectly
-
D
The user interface may not meet accessibility standards