In the V-model, what is the relationship between test levels and development phases?
-
A
Each test level corresponds to a development phase on the opposite side of the V
-
B
Test levels replace development phases to save time
-
C
Only system testing and unit testing exist in the V-model
-
D
Test levels are entirely independent of development activities