A test manager is creating the master test plan for a large project. According to the IEEE 829 standard, which of the following items should be included in the 'Risks and Contingencies' section of the test plan?
-
A
A list of all defects found in previous projects.
-
B
Detailed test procedures for high-risk features.
-
C
Potential issues that could jeopardize the test project, and the planned responses.
-
D
The final pass/fail criteria for system testing.