What does the Critical Path Method (CPM) identify in a GIS project schedule?
-
A
The highest-cost data layers
-
B
The longest sequence of dependent tasks determining minimum project duration
-
C
The servers with the most processing load
-
D
The riskiest spatial analysis workflows