In a GIS project, what does a Work Breakdown Structure (WBS) primarily help you accomplish?
-
A
Automatically generate map symbology
-
B
Decompose project scope into manageable deliverables
-
C
Set coordinate reference systems
-
D
Schedule satellite imagery acquisition