A project manager is launching a new web-based GIS application for a municipal planning department. After initial meetings, stakeholders have provided a long list of desired features. To prevent scope creep and establish a clear, shared understanding of the project's boundaries, what is the MOST critical document to create and get approved next?
-
A
A detailed Gantt Chart
-
B
A Project Scope Statement
-
C
A Risk Register
-
D
A Communications Management Plan