A project team uses a decision tree to evaluate two alternative approaches. Decision trees are PRIMARILY used to:
-
A
Identify stakeholder influence on risks
-
B
Calculate EMV across multiple decision paths with uncertain outcomes
-
C
Assign risk owners from the team
-
D
Rank risks in the risk register