A project manager identifies that a key vendor may go out of business before delivering critical software. What type of risk response is BEST suited for this scenario?
-
A
Accept the risk and document it
-
B
Transfer the risk to the vendor via contract penalties
-
C
Mitigate by qualifying an alternative vendor
-
D
Avoid the risk by canceling the project