During project execution, a team member consistently delivers work that does not meet quality standards. What should the project manager do FIRST?
-
A
Replace the team member immediately
-
B
Document the issue in the risk register
-
C
Identify the root cause and provide coaching or training
-
D
Escalate to the functional manager