A project manager notices that the critical path has shifted after a key deliverable slipped by three days. What is the FIRST action they should take?
-
A
Issue a change request immediately
-
B
Re-baseline the project schedule
-
C
Analyze the impact on the project end date
-
D
Notify the sponsor of the delay