A project manager is preparing a presentation for the project steering committee. Which content approach is MOST effective?
-
A
Include all project details to demonstrate thoroughness
-
B
Focus on decisions needed, key risks, and milestone status
-
C
Present only positive updates to maintain stakeholder confidence
-
D
Delegate the presentation to the technical lead