What is the significance of the owner defining 'best value' criteria before issuing a design-build RFP?
-
A
It allows the owner to change evaluation criteria after proposals are received
-
B
It ensures proposers understand how proposals will be scored and reduces protest risk
-
C
It requires the owner to select the lowest-cost proposer regardless of technical quality
-
D
It eliminates the need for a technical proposal from design-build teams