Immediately following contract award for a design-build project, what is the primary purpose of the project kick-off meeting?
Select your answer
A
To finalize the selection of major subcontractors and suppliers.
B
To mobilize construction equipment and personnel to the site.
C
To align the entire integrated team on project goals, communication protocols, and team culture.
D
To obtain the final notice to proceed from the owner.