DBIA Owner Engagement 5 — Questions and Answers
Question 1: What is the significance of the owner defining 'best value' criteria before issuing a design-build RFP?
- It allows the owner to change evaluation criteria after proposals are received
- It ensures proposers understand how proposals will be scored and reduces protest risk (Correct answer)
- It requires the owner to select the lowest-cost proposer regardless of technical quality
- It eliminates the need for a technical proposal from design-build teams
Correct answer: It ensures proposers understand how proposals will be scored and reduces protest risk
Pre-defined best value criteria create a transparent evaluation framework, align proposals with owner priorities, and reduce the risk of procurement protests.
Question 2: How does an owner's failure to make timely decisions impact a design-build project?
- It has no impact because the design-builder can proceed independently
- It can delay the project schedule and entitle the design-builder to time extensions and additional compensation (Correct answer)
- It automatically transfers schedule risk to the owner's insurer
- It voids the design-builder's performance guarantees
Correct answer: It can delay the project schedule and entitle the design-builder to time extensions and additional compensation
Late owner decisions create schedule delays and, under most DBIA contracts, entitle the design-builder to seek equitable adjustments for time and cost impacts caused by owner-controlled delays.
Question 3: What is the owner's responsibility regarding environmental permits on a typical design-build project?
- The design-builder obtains all environmental permits as part of its fixed-price contract
- The owner typically obtains major environmental permits before project award, while the design-builder handles construction permits (Correct answer)
- The design-builder and owner share equal responsibility for all permits without distinction
- Environmental permits are the responsibility of the local jurisdiction and neither party
Correct answer: The owner typically obtains major environmental permits before project award, while the design-builder handles construction permits
Owners typically secure major environmental permits (NEPA, wetlands, etc.) pre-procurement to reduce RFP uncertainty, while design-builders obtain construction-phase permits.
Question 4: Why is it important for an owner to establish a project controls system that interfaces with the design-builder's reporting?
- To allow the owner to override the design-builder's schedule at any time
- To maintain independent visibility into cost and schedule status for informed decision-making throughout the project (Correct answer)
- To replace the design-builder's internal project management systems
- To satisfy insurance requirements for project completion bonds
Correct answer: To maintain independent visibility into cost and schedule status for informed decision-making throughout the project
An integrated project controls interface gives the owner objective cost and schedule data, enabling proactive decision-making rather than relying solely on the design-builder's reporting.
Question 5: What is the most appropriate owner action when a design-builder's preliminary design significantly exceeds the project budget?
- Immediately terminate the contract for default
- Engage collaboratively with the design-builder to identify scope reductions or value engineering solutions that align with the budget (Correct answer)
- Accept the budget overrun and fund the difference
- Issue a unilateral change order reducing the design-builder's fee
Correct answer: Engage collaboratively with the design-builder to identify scope reductions or value engineering solutions that align with the budget
DBIA's collaborative model calls for owner and design-builder to jointly solve budget challenges through scope adjustment or value engineering rather than adversarial responses.
Question 6: Which characteristic of an owner's organization most supports successful design-build project delivery?
- A large internal design staff that can independently verify every design calculation
- Decision-making authority vested in the owner's project representative to enable timely approvals (Correct answer)
- A procurement department that evaluates design-build proposals on price alone
- A policy requiring all changes to be reviewed by the full owner board before proceeding
Correct answer: Decision-making authority vested in the owner's project representative to enable timely approvals
Empowering the owner's project representative with decision-making authority enables timely responses to design-builder requests, maintaining project momentum and preventing owner-caused delays.
Question 7: How should an owner structure its commissioning requirements in a design-build RFP to optimize project outcomes?
- Omit commissioning requirements from the RFP and address them after construction is complete
- Include commissioning requirements in the OPR and RFP so the design-builder can integrate commissioning into design and construction planning (Correct answer)
- Hire a separate commissioning agent independently of the design-builder without informing them during procurement
- Require the design-builder to use the owner's in-house commissioning team regardless of design decisions
Correct answer: Include commissioning requirements in the OPR and RFP so the design-builder can integrate commissioning into design and construction planning
Including commissioning requirements in the RFP allows the design-builder to plan for testing and verification from project inception, reducing startup issues and ensuring systems meet OPR performance standards.
What is the significance of the owner defining 'best value' criteria before issuing a design-build RFP?