DBIA Cheat Sheet 2026

The 30 highest-yield DBIA facts, distilled from real exam questions. Print it, save it as a PDF, or study it here — free, no sign-up.

100 questions
120 min time limit
72.00% to pass
  1. In design-build contracts following DBIA model language, the contractual warranty period for the completed work typically begins at: Substantial completion
  2. What is DBIA's recommended approach to risk allocation in design-build contracts? Allocate each risk to the party best able to manage, mitigate, or absorb that risk
  3. A university campus renovation using design-build would most likely establish the Owner's Project Requirements (OPR) to address which unique need? Phasing to maintain campus operations and academic calendar
  4. In a progressive design-build delivery, when is the contract price typically finalized? After the design reaches a defined milestone sufficient for accurate pricing
  5. Which of the following is NOT a typical benefit attributed to design-build delivery? Greater owner control over detailed design decisions throughout the project
  6. In the correctional facilities sector, which design-build delivery challenge is most unique compared to other building types? Coordinating with security and operational staff during programming
  7. Which technique BEST reduces design-to-construction coordination errors on complex design-build projects? Using Building Information Modeling (BIM) with clash detection across disciplines
  8. Under a Cost-Plus-Fee design-build contract, the owner's primary financial protection mechanism is typically: A Guaranteed Maximum Price (GMP) provision
  9. In a design-build project, the owner withholds a higher-than-typical retainage percentage. What risk does this primarily impose on the design-builder? Cash flow risk and working capital strain
  10. In design-build contracting, a 'risk-adjusted contingency' differs from a standard contingency in that it: Is calculated based on probability and impact analysis of specific identified risks
  11. What does 'schedule float' (also called slack) represent in a project schedule? The amount of time an activity can be delayed without delaying the project completion date
  12. Which contract type places the most financial risk on the design-builder? Lump sum/fixed price
  13. In a military design-build project, which document typically defines the owner's requirements and serves as the basis for DB team proposals? Request for Proposal with Performance Work Statement (PWS)
  14. How does the DBIA Code address a member's obligation to report suspected violations of the Code by other DBIA members? Members are encouraged to report credible violations through appropriate DBIA channels
  15. When scoring design-build proposals, weighting technical factors more heavily than price is most appropriate when: The project is complex, innovative, or involves significant technical risk
  16. Which of the following RFP evaluation criteria directly assesses a proposer's ability to complete a project on time? Schedule approach and critical path methodology
  17. In design-build dispute resolution, what is the typical hierarchy of escalation in DBIA standard documents? Direct negotiation → Mediation → Arbitration or Litigation
  18. A design-build team discovers previously unknown underground utilities during excavation. Under a well-drafted contract, this risk is most likely classified as: An owner-retained subsurface risk eligible for a contract adjustment
  19. What is a 'not-to-exceed' (NTE) price in design-build contracting? A preliminary price ceiling established early in the project before a formal GMP is set
  20. What is a Guaranteed Maximum Price (GMP) in the context of design-build delivery? A contract ceiling beyond which the owner does not pay cost overruns
  21. A design-build contract's 'warranty' provision most commonly requires the design-builder to: Correct defective work discovered within a specified period after substantial completion
  22. The Design-Build Institute of America's Political Action Committee (PAC) is primarily used for which purpose? Supporting candidates and elected officials who champion design-build-friendly legislation
  23. In federal design-build procurement under FAR Part 36, the two-phase selection process Phase 1 is used to: Shortlist qualified offerors before requesting full technical proposals in Phase 2
  24. Under the DBIA Code of Professional Conduct, which statement best describes a member's duty regarding sustainability and environmental responsibility? Members should consider environmental impacts and promote sustainable practices
  25. In the public sector, which procurement method is most compatible with design-build when the owner wants to consider both qualifications and price? Best-value selection
  26. What is the role of the stipend in a competitive design-build procurement? Partial compensation paid to unsuccessful proposers for their proposal costs
  27. Which document, issued after a design-build project is awarded, formally authorizes the design-builder to begin work? Notice to Proceed (NTP)
  28. A state legislature is considering a sunset provision in a design-build enabling statute. What does a sunset provision mean in this context? The enabling authority automatically expires after a specified period unless renewed
  29. In a design-build competition, a proposal that is deemed 'non-responsive' will: Be disqualified from consideration without further evaluation
  30. In which construction sector has design-build seen the most rapid growth in recent years? Water and wastewater infrastructure
Turn these facts into recall:
Was this helpful?