In records management projects, what does a Work Breakdown Structure (WBS) primarily help accomplish?
-
A
Allocate budget across fiscal years
-
B
Decompose project scope into manageable deliverables
-
C
Schedule vendor contract renewals
-
D
Identify stakeholder communication preferences