The critical path in a project schedule is BEST defined as:
-
A
The sequence of tasks with the most budget allocated
-
B
The longest duration path of dependent tasks that determines project end date
-
C
The list of highest-risk activities in the project
-
D
Tasks assigned to the most senior team members