CPHIMS CPHIMS Project Management Questions and Answers 2 — Questions and Answers
Question 1: The critical path in a project schedule is BEST defined as:
- The sequence of tasks with the most budget allocated
- The longest duration path of dependent tasks that determines project end date (Correct answer)
- The list of highest-risk activities in the project
- Tasks assigned to the most senior team members
Correct answer: The longest duration path of dependent tasks that determines project end date
The critical path is the longest sequence of dependent tasks; any delay on these tasks directly delays the overall project completion date.
Question 2: Which risk response strategy involves transferring the financial impact of a risk to a third party?
- Avoidance
- Mitigation
- Transfer (Correct answer)
- Acceptance
Correct answer: Transfer
Risk transfer shifts the financial consequence of a risk to another party, commonly through insurance or contractual provisions with vendors.
Question 3: Earned Value Management (EVM) uses which metrics to measure project performance?
- Planned Value, Earned Value, and Actual Cost (Correct answer)
- Budget, Schedule, and Quality baselines
- Return on Investment, Net Present Value, and Payback Period
- Scope, Time, and Cost variances only
Correct answer: Planned Value, Earned Value, and Actual Cost
EVM integrates Planned Value (PV), Earned Value (EV), and Actual Cost (AC) to objectively measure schedule and cost performance.
Question 4: A lessons-learned document should be completed:
- Only when the project fails to meet its objectives
- At project closure to capture knowledge for future projects (Correct answer)
- Before the project kickoff meeting
- Only by the project sponsor
Correct answer: At project closure to capture knowledge for future projects
Lessons learned are formally documented at project closure to preserve knowledge that improves future healthcare IT implementations.
Question 5: Which procurement document is used to solicit proposals from vendors for a hospital's new health information system?
- Statement of Work (SOW)
- Request for Proposal (RFP) (Correct answer)
- Non-Disclosure Agreement (NDA)
- Service Level Agreement (SLA)
Correct answer: Request for Proposal (RFP)
An RFP invites vendors to submit detailed proposals describing their solutions, pricing, and qualifications for a defined healthcare IT need.
Question 6: Stakeholder engagement planning in a healthcare IT project PRIMARILY aims to:
- Minimize the number of people involved in the project
- Identify stakeholder interests and develop strategies to maintain appropriate involvement (Correct answer)
- Ensure only clinical staff are consulted during design
- Delegate all communication to the vendor
Correct answer: Identify stakeholder interests and develop strategies to maintain appropriate involvement
Stakeholder engagement planning identifies each stakeholder's needs and interests to develop targeted communication and involvement strategies throughout the project.