The critical path in a project schedule is BEST defined as:
Select your answer
A
The sequence of tasks with the most budget allocated
B
The longest duration path of dependent tasks that determines project end date
C
The list of highest-risk activities in the project
D
Tasks assigned to the most senior team members
Hint