A project manager discovers a key stakeholder was not included in a critical decision email chain. What is the best immediate action?
-
A
Ignore it since the decision is already made
-
B
Forward the email thread and schedule a briefing to bring them up to speed
-
C
Ask another stakeholder to inform them informally
-
D
Wait until the next scheduled meeting to address it