A project manager notices her team misses deadlines because members don't speak up when they're behind. Which communication strategy best addresses this?
-
A
Send daily status report emails
-
B
Hold brief daily stand-ups where each member states their progress and blockers
-
C
Post a shared spreadsheet for updates
-
D
Increase the frequency of formal reviews