A roofing contractor requests a 50% deposit before starting a $200,000 replacement project. What is the BEST practice for the association?
-
A
Pay the full amount upfront to secure scheduling
-
B
Negotiate a smaller deposit and tie remaining payments to project milestones
-
C
Refuse any deposit and pay only upon full completion
-
D
Pay the deposit from the operating account regardless of reserve balance