A change is deemed 'standard' in an ITIL framework. What risk characteristic typically qualifies it as standard?
-
A
It has been formally escalated to the CAB for review
-
B
It is low risk, well-understood, and follows a pre-approved procedure
-
C
It requires a full business impact analysis before approval
-
D
It involves significant infrastructure modification