The CTCM certification program validates your knowledge of procurement planning, contract formation, and contract oversight. It is distinct from the CTPM certification, focusing specifically on post-award activities. Practice with the free CTCM - Certified Texas Contract Manager practice test on PracticeTestGeeks (9 questions with answer explanations).

If you are searching for a CTCM practice test online, start with the free questions on this page: every answer comes with an explanation, and the study notes below cover the CTCM exam topics in order.

The CTCM takes about 2 hours and costs $120[1] (Texas Comptroller of Public Accounts - Statewide Procurement Division, verified Oct 27, 2026).

  • A maximum time limit of two hours is allowed for the Certified Texas Contract Manager exam.[1]
  • Candidates must achieve at least an 80% score to pass the Certified Texas Contract Manager exam.[2]
  • The Certified Texas Contract Manager exam costs $120 when paid by money order, check, or credit card, and $130 when paying with a purchase order.[1]
  • Candidates may repeat the Certified Texas Contract Manager exam twice after an initial failure for a total of three attempts before being required to retake the course.[2]
  • The Certified Texas Contract Manager certification is valid for three years.[3]
  • The Certified Texas Contract Manager exam is delivered as a paper exam with an answer bubble-in sheet administered at UT Austin Testing and Evaluation Services or an approved alternate university or college testing center.[1]
  • Eligibility for the Certified Texas Contract Manager exam requires completion of the training course and status as a current Texas state or local government employee, qualifying student or graduate, or retained contractor.[2]

Numbers in brackets link to the official sources listed under Sources & last verified. Dates that have passed are removed automatically.

CTCM Exam at a Glance

ItemDetailSource ยท Verified
Time limit2 hours maximum[1]Texas Comptroller of Public Accounts - Statewide Procurement Division ยท Oct 27, 2026
Passing score80%[2]Texas Comptroller of Public Accounts - Statewide Procurement Division ยท Oct 27, 2026
Exam fee$120 (money order, check or card); $130 with a purchase order[1]Texas Comptroller of Public Accounts - Statewide Procurement Division ยท Oct 27, 2026
Retake policy3 attempts total; retake the course after 3 failures[2]Texas Comptroller of Public Accounts - Statewide Procurement Division ยท Oct 27, 2026
Validity3 years[3]Texas Comptroller of Public Accounts - Statewide Procurement Division ยท Oct 27, 2026
DeliveryPaper exam (bubble-in answer sheet) at UT Austin Testing and Evaluation Services or an approved university/college testing site[1]Texas Comptroller of Public Accounts - Statewide Procurement Division ยท Oct 27, 2026
EligibilityCurrent Texas state or local government employee (or qualifying student/contractor) who has completed the course[2]Texas Comptroller of Public Accounts - Statewide Procurement Division ยท Oct 27, 2026
Late registration deadlineOne-time 60-day extension for $50[2]Texas Comptroller of Public Accounts - Statewide Procurement Division ยท Oct 27, 2026
Registration deadlineWithin 60 days of enrollment[1]Texas Comptroller of Public Accounts - Statewide Procurement Division ยท Oct 27, 2026
Testing windowWithin 3 months of completing the course[2]Texas Comptroller of Public Accounts - Statewide Procurement Division ยท Oct 27, 2026

What changed for CTCM in 2026

  • Oct 27, 2026: Registration deadline changed to Within 60 days of enrollment (previously Exam must be taken within 60 days of enrollment).[1]
  • Oct 27, 2026: Testing window changed to Within 3 months of completing the course (previously Within 3 months of the course; 60 days from enrollment).[2]
  • Oct 27, 2026: Delivery changed to Paper exam (bubble-in answer sheet) at UT Austin Testing and Evaluation Services or an approved university/college testing site (previously Paper exam (bubble sheet) at UT Austin Testing and Evaluation Services or an approved university/college proctor).[1]

Free CTCM - Certified Texas Contract Manager Study Tools

Interactive CTCM - Certified Texas Contract Manager resources on PracticeTestGeeks, free to start:

Certified Texas Contract Manager - Certified Texas Contract Manager study guide

According to Texas Comptroller of Public Accounts - Statewide Procurement Division, โ€œTo receive certification, you must receive at least an 80% passing score on the exam.โ€[2]

CTCM content outline and where to practise each area

The content areas below are copied from the official CTCM content outline published by Texas Comptroller of Public Accounts - Statewide Procurement Division. The right-hand column shows which of our practice sets covers it.

Official content areaPractice on this site
Section 1: The Statewide Procurement Division[4]CTCM Texas Procurement Laws and Regulations
Learn what the Statewide Procurement Division does, which state laws give it authority, and which programs agencies must follow, such as the HUB program.
Section 2: The Purpose of a Contract[4]CTCM - Certified Texas Contract Manager Pr...
Practise naming the basic elements of a valid contract and explaining how a well-planned contract protects the state and sets clear expectations for the vendor.
Section 3: Reading and Understanding a Contract[4]CTCM - Certified Texas Contract Manager Ri...
Read contract terms closely: who carries which risk, what the vendor must deliver, and how clauses on payment, insurance and remedies work together.
Section 4: Contract Administration[4]CTCM - Certified Texas Contract Manager Co...
Practise day-to-day contract management tasks: monitoring vendor performance, approving payments, documenting every modification and closing out the contract.
Section 5: Ethical Contract Management[4]CTCM - Certified Texas Contract Manager Le...
Learn to spot conflicts of interest, gift and disclosure problems, and other situations where a contract manager must step back or report.

CTCM Practice Test Questions

Prepare for the CTCM - Certified Texas Contract Manager exam with our free practice test modules. Each quiz covers key topics to help you pass on your first try.

CTCM - Certified Texas Contract Manager Co...

CTCM Exam Questions covering - Certified Texas Contract Manager Contract Administration Principles. Master CTCM Test concepts for certification prep.

CTCM - Certified Texas Contract Manager Co...

Free CTCM Practice Test featuring - Certified Texas Contract Manager Contract Closeout Procedures. Improve your CTCM Exam score with mock test prep.

CTCM - Certified Texas Contract Manager Co...

CTCM Mock Exam on - Certified Texas Contract Manager Contract Modifications and Changes. CTCM Study Guide questions to pass on your first try.

CTCM - Certified Texas Contract Manager Le...

CTCM Test Prep for - Certified Texas Contract Manager Legal and Ethical Compliance. Practice CTCM Quiz questions and boost your score.

CTCM - Certified Texas Contract Manager Ne...

CTCM Questions and Answers on - Certified Texas Contract Manager Negotiation and Dispute Resolution. Free CTCM practice for exam readiness.

CTCM - Certified Texas Contract Manager Pr...

CTCM Mock Test covering - Certified Texas Contract Manager Procurement Planning and Formation. Online CTCM Test practice with instant feedback.

CTCM - Certified Texas Contract Manager Ri...

Free CTCM Quiz on - Certified Texas Contract Manager Risk Assessment and Management. CTCM Exam prep questions with detailed explanations.

CTCM - Certified Texas Contract Manager Ve...

CTCM Practice Questions for - Certified Texas Contract Manager Vendor Performance and Monitoring. Build confidence for your CTCM certification exam.

CTCM Contract Financing and Payment Manage...

CTCM Test Online for Contract Financing and Payment Management. Free practice with instant results and feedback.

CTCM Solicitation and Source Selection

CTCM Study Material on Solicitation and Source Selection. Prepare effectively with real exam-style questions.

CTCM Texas Procurement Laws and Regulations

Free CTCM Test covering Texas Procurement Laws and Regulations. Practice and track your CTCM exam readiness.

CTCM Contract Administration & Management

CTCM Exam Questions covering Contract Administration & Management. Master CTCM Test concepts for certification prep.

CTCM Contract Oversight & Performance Moni...

Free CTCM Practice Test featuring Contract Oversight & Performance Monitoring. Improve your CTCM Exam score with mock test prep.

CTCM Ethics & Legal Compliance

CTCM Mock Exam on Ethics & Legal Compliance. CTCM Study Guide questions to pass on your first try.

CTCM Procurement Planning & Execution

CTCM Test Prep for Procurement Planning & Execution. Practice CTCM Quiz questions and boost your score.

Worked examples: how to reason through CTCM questions

These are practice questions written for this site, not questions from the real exam. Each explanation shows why the right answer is right and why the others are wrong.

Example 1

Question: In Texas, which program requires state agencies to make a good-faith effort to include Historically Underutilized Businesses in their procurement processes?

  1. Texas Enterprise Fund Program
  2. HUB Program under Texas Government Code Chapter 2161
  3. State Use Program
  4. Texas Vendor Performance Program

Answer: B. HUB Program under Texas Government Code Chapter 2161

Explanation:

B is correct. Texas Government Code Chapter 2161 creates the Historically Underutilized Business (HUB) program. It requires state agencies to make a good-faith effort to include HUBs in their purchasing, for example through HUB subcontracting plans.

  • A is wrong: the Texas Enterprise Fund is an economic development incentive. It has no rules about who takes part in agency purchasing.
  • C is wrong: the State Use Program sends certain purchases to community rehabilitation programs that employ people with disabilities. It is a separate program, not the HUB good-faith effort.
  • D is wrong: vendor performance tracking records how contractors performed after the work. It does not set participation requirements.

Rule to remember: if a question mentions historically underutilized businesses or a good-faith effort, the answer is the HUB program.

Example 2

Question: A contract manager needs to update the agency's official point-of-contact information listed in the contract due to a staff retirement. This action does not affect the price, scope, or delivery schedule. The most appropriate mechanism to formalize this change is a:

  1. Bilateral amendment requiring contractor negotiation.
  2. Constructive change memo for the file.
  3. Unilateral administrative modification.
  4. Request for equitable adjustment.

Answer: C. Unilateral administrative modification.

Explanation:

C is correct. Changing the agency's point of contact is a purely administrative change. Price, scope, schedule and the vendor's rights all stay the same, so the agency can record the change on its own with a unilateral administrative modification.

  • A is wrong: you need a bilateral amendment, signed by both parties, only when a change affects what both sides agreed to. Here nothing substantive changes, so there is nothing to negotiate.
  • B is wrong: a constructive change happens when the agency's actions informally change the work without a formal modification. It is a problem to avoid, not a way to formalize anything, and a memo to the file does not modify the contract.
  • D is wrong: a vendor files a request for equitable adjustment to ask for more money or time. This change costs the vendor nothing.

Rule to remember: administrative changes can be unilateral. Anything that touches price, scope or schedule must be bilateral.

Example 3

Question: When should contract modifications be documented?

  1. Only for changes over $10,000
  2. For all changes, regardless of size or significance
  3. At the end of the contract term
  4. Only when requested by the vendor

Answer: B. For all changes, regardless of size or significance

Explanation:

B is correct. Every change to a contract must be documented in writing and kept in the contract file, however small it is. That record makes the agreement enforceable, prevents disputes over what was agreed, and gives auditors a clear trail.

  • A is wrong: there is no dollar threshold, such as $10,000, below which changes can go undocumented. A small change still changes what each party owes.
  • C is wrong: waiting until the end of the term means the contract on file does not match the real agreement while the work is going on, and memories fade before any dispute or audit.
  • D is wrong: keeping the contract record is the agency's job no matter who asked for the change.

Rule to remember: if it changes the contract, document it when it happens.

How to use these practice tests

Start right after the course. You have 3 months after finishing the course to test, and once you enroll you must sit the exam within 60 days. Pick a test date early, while the course is still fresh, so you are not paying the $50 extension fee for lack of planning.

  1. Reread the official material by section. Use your course manual and the Comptroller's procurement and contract management guidance. Follow the course's section order: the Statewide Procurement Division, the purpose of a contract, reading a contract, contract administration, and ethics.
  2. Take one practice set per section. Use the matching set from the table above. After each set, read the explanation for every question you missed or guessed. Write the rule in your own words, then check it against the official material. Our questions are written by us, not taken from the real exam.
  3. Go back to weak areas. Retake the sets where you missed the most, plus the related sets on modifications, closeout and vendor monitoring.
  4. Do a timed mixed run. Do several sets in a row within 2 hours, without notes, and aim to score well above 80% before test day.
  5. Prepare for paper. Practise marking answers on paper, and pack your own #2 pencil.

CTCM Exam Flashcards

Quick review for the Certified Texas Contract Manager exam

โš–๏ธWhat is the role of the Texas Ethics Commission?

To administer and enforce laws regarding ethics, financial disclosure, and standards of conduct.

TRY CTCM MOCK EXAM

๐Ÿ”„When should a contract change order be issued?

When there is a modification to the scope, price, or timeline that differs from the original agreement.

ACCESS CTCM STUDY GUIDE

๐Ÿ’ฐWhat is "Best Value" procurement?

Selecting a vendor based on a combination of price, quality, and performance factors.

PRACTICE CTCM TEST NOW

๐Ÿ“ŠWhat is vendor performance monitoring?

Tracking a vendor's progress and deliverables to ensure they meet contract requirements.

GET CTCM EXAM PREP

CTCM Exam Study Guide

Our Certified Texas Contract Manager certification study guide breaks down the essential information you need. Navigate through the tabs below to understand the CTCM basics, format, registration, results, and salary expectations.

What is the CTCM certification?
The Certified Texas Contract Manager (CTCM) certification validates expertise in managing contracts for Texas state agencies. It covers the entire contract lifecycle.
Who needs the CTCM certification?
State agency employees in Texas who are involved in contract management, administration, or oversight are typically required to obtain CTCM certification.
What is the difference between CTPM and CTCM?
CTPM (Purchaser) focuses on the acquisition process, while CTCM (Contract Manager) focuses on managing the contract after it has been awarded.
Is the CTCM exam hard?
The CTCM exam can be challenging as it tests specific knowledge of Texas statutes and the Contract Management Guide. Thorough preparation is essential.

Review the Certified Texas Contract Manager study guide provided by the Comptroller. Focus heavily on the "Contract Administration" section, as it makes up a large portion of the CTCM exam questions.

The estimated total CTCM certification cost is around $400-$500. Many Texas state agencies will cover the CTCM training and exam fees for their employees.

Mastering the Certified Texas Contract Manager (CTCM) Certification Exam - Certified Texas Contract Manager exam preparation

CTCM Test Day Checklist

  • โœ“Valid Photo ID (Driver's License)
  • โœ“Exam Confirmation Email
  • โœ“Arrive 15 Minutes Early
  • โœ“Leave Personal Items in Car
  • โœ“Review CTCM Study Guide
  • โœ“Know Testing Center Location
  • โœ“Bring Required Forms
  • โœ“Relax and Be Confident

Start Your CTCM Prep

Don't wait to advance your career. Take our free CTCM practice test today and ensure you're ready for the Certified Texas Contract Manager exam.

Ensure you complete your CTCM continuing education hours before your certification expiration date to avoid penalties or lapsing status.

โœ…Pros
  • +Validates your knowledge and skills objectively
  • +Increases job market competitiveness
  • +Provides structured learning goals
  • +Networking opportunities with other certified professionals
โŒCons
  • โˆ’Study materials can be expensive
  • โˆ’Exam anxiety can affect performance
  • โˆ’Requires dedicated preparation time
  • โˆ’Retake fees apply if you don't pass

Pros and Cons at a Glance

ProsCons
Validates your knowledge and skills objectivelyStudy materials can be expensive
Increases job market competitivenessExam anxiety can affect performance
Provides structured learning goalsRequires dedicated preparation time
Networking opportunities with other certified professionalsRetake fees apply if you don't pass

Sample CTCM - Certified Texas Contract Manager Practice Questions

Try these questions from our free CTCM - Certified Texas Contract Manager practice tests. The correct answer and an explanation follow each question.

  1. A Certified Texas Contract Manager is creating a contract closeout checklist. All of the following are essential elements to include EXCEPT:

    • A. Verifying that all goods, services, and reports have been delivered and formally accepted.
    • B. Ensuring all invoices have been paid and conducting a final funds reconciliation.
    • C. Confirming that the contractor has initiated the process for contract renewal.
    • D. Documenting the disposition of any state-furnished or contractor-acquired property.

Answer: C. Confirming that the contractor has initiated the process for contract renewal.

Contract closeout is the process of finalizing all activities for a completed contract. Contract renewal is a separate, future procurement action and is not part of closing out the existing contract. The other options are all core administrative tasks required for a proper closeout.

  • A director at a Texas state agency, who has authority over contract approvals, wants to approve a professional services contract with a consulting firm where their son-in-law is a principal partner. Which of the following Texas statutes would this action most directly violate?

    • A. The Anti-Nepotism Statute (Gov't Code Ch. 573)
    • B. The Public Information Act (Gov't Code Ch. 552)
    • C. The State Purchasing Act (Gov't Code Ch. 2155)
    • D. The Professional Services Procurement Act (Gov't Code Ch. 2254)
  • Answer: A. The Anti-Nepotism Statute (Gov't Code Ch. 573)

    Texas Government Code Chapter 573, the anti-nepotism law, prohibits a public official from appointing, or voting for the appointment of, a close relative to a position compensated by public funds. A son-in-law is a relative within the second degree of affinity, which is a prohibited degree. Attorney General opinions have clarified that this can extend to private contractors, making this action a violation of the statute.

  • What is 'best value' procurement in Texas, and how does it differ from low-bid procurement?

    • A. Best value always selects the highest-priced vendor; low-bid selects the cheapest
    • B. Best value considers multiple factors including price, quality, and vendor capability; low-bid awards only on price
    • C. Best value is used only for IT procurement; low-bid is used for construction
    • D. Best value requires HUB participation; low-bid does not
  • Answer: B. Best value considers multiple factors including price, quality, and vendor capability; low-bid awards only on price

    Best value procurement evaluates factors such as price, quality, service, and past performance holistically, whereas low-bid procurement awards solely to the lowest responsive price.

  • What is the benefit of using performance scorecards for contract monitoring?

    • A. To make contractors compete against each other unnecessarily
    • B. To provide standardized, objective performance evaluation
    • C. To eliminate all contract documentation
    • D. To reduce the frequency of performance reviews
  • Answer: B. To provide standardized, objective performance evaluation

    Performance scorecards are valuable tools in contract monitoring because they provide a standardized and objective method for evaluating contractor performance against agreed-upon metrics. By using consistent criteria and quantifiable measures, scorecards reduce subjectivity and facilitate clear communication regarding expectations and results. This systematic approach helps ensure fair assessment and drives continuous improvement in service delivery.

    Take the full CTCM - Certified Texas Contract Manager practice test

    CTCM Questions and Answers

    Official Resources

    Sources & last verified

    1. Texas Comptroller of Public Accounts - Statewide Procurement Division โ€” time limit, exam fee, delivery, registration deadline (official source). โ€œA two-hour maximum time limit is allowed for each exam.โ€ Verified Oct 27, 2026 ยท source checked Oct 21, 2026.
    2. Texas Comptroller of Public Accounts - Statewide Procurement Division โ€” passing score, retake policy, eligibility, late registration deadline (official source). โ€œTo receive certification, you must receive at least an 80% passing score on the exam.โ€ Verified Oct 27, 2026 ยท source checked Oct 21, 2026.
    3. Texas Comptroller of Public Accounts - Statewide Procurement Division โ€” validity (official source). โ€œCertifications are issued for three (3) years for Certified Texas Contract Developers and Certified Texas Contract Managers.โ€ Verified Oct 27, 2026 ยท source checked Oct 21, 2026.
    4. Texas Comptroller of Public Accounts - Statewide Procurement Division โ€” other (official source). โ€œsection 1 the statewide procurement divisionโ€ Verified Oct 29, 2026.

    How we verify: editorial & fact-checking policy. Report an error: contact us.

    How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

    Sources & references

    Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

    1. comptroller.texas.gov โ€” Eligibility, late registration, passing score, retake policy, test dates, test delivery, fees, registration deadline, time limit, score validity ยท verified Oct 2026