A construction manager notices that a major subcontractor's activities consistently appear on the critical path. What proactive step should be taken?
-
A
Replace the subcontractor immediately
-
B
Increase the frequency of schedule updates and coordination meetings with that subcontractor
-
C
Assign float from non-critical activities to their work
-
D
Remove their activities from the schedule baseline