A project team uses Monte Carlo simulation to analyze schedule risk. The output shows the P80 completion date is October 15. What does P80 mean?
-
A
80% of activities are on the critical path
-
B
There is an 80% probability the project will finish by October 15
-
C
The project has an 80% schedule performance index
-
D
80% of risks have been mitigated by October 15